VANCOUVER, British Columbia, Dec. 08, 2020 (GLOBE NEWSWIRE) — Novo Resources Corp. (“ Novo ” or the “ Company ”) (TSX-V: NVO & NVO.WT; OTCQX: NSRPF) is pleased to announce it has taken delivery of its Steinert KSS mechanical sorter and provides an operational update from its Beatons Creek gold project (“ Beatons Creek ”) and Nullagine processing facility ( “Golden Eagle Mill” )

Mechanical orting pdate :

  • The Steinert KSS mechanical sorter has arrived into the port of Fremantle (Perth) and is currently being delivered to Steinert’s test facility;
  • Orders have been placed for all long lead items (feeder hopper, feeder conveyor, discharge conveyors). Pre-assembly will occur at Steinert / OPS facility in Bibra Lake (Perth) prior to mobilization to site;
  • Planning is well advanced with design of support infrastructure – compressed air, power, cyclone rated shelter / offices; and
  • The Comet Well / Purdy’s Reward mechanical sorting trial remains on track to commence in April 2021 subject to receiving requisite approvals from the Department of Mines, Industry Regulation, and Safety and the Department of Water and Environmental Regulation. Ngarluma Aboriginal Corporation approval has been granted.

Beatons Creek and Nullagine Gold Project Update:

Development at Beatons Creek and refurbishment at the Golden Eagle Mill continue to progress safely, on schedule and within budget. Recent key milestones achieved include:

  • Mining contractor systems alignment and pre-mobilization works proceeding to plan to support arrival of first plant and personnel from December 14 th ;
  • Grade control drilling now operating day and night shifts as planned; and
  • Site personnel (including contractors) now totaling 80.

CLICK HERE to read the rest of the news release.

Leave a Reply

Your email address will not be published. Required fields are marked *

Name *
Email *
Website